Overall renovation of the Bäumlihof school complex, Basel

2017

Timbatec Holzbauingenieure was entrusted with the planning and management of the replacement of the existing façade for the complete renovation of the Bäumlihof school complex. 18-millimeter-thick glass-fiber-reinforced concrete panels were mounted on the wooden structure.

Facts and images
Construction Data
Involved
Articles
Temporary support with tree trunks
Temporary support with tree trunks
Connection of the wooden structure to the existing concrete elements
Connection of the wooden structure to the existing concrete elements
Sketch facade detail above
Sketch facade detail above
Sketch facade detail below
Sketch facade detail below

The project
The Bäumlihof Gymnasium offers space for around 1500 students. About forty years after its opening, a complete renovation was due. During the extensive renovation measures, the electrical, sanitary and heating systems were replaced, the buildings were structurally strengthened and brought up to date from an energy point of view. For this purpose, the old concrete facade was completely dismantled and replaced by a wooden construction. The outer layer was installed on top of this. A new filigree façade made of thin glass-fiber-reinforced concrete panels now envelops the building. Furthermore, the wooden structure supports the large-format wood-aluminum windows with their opening casements. Timbatec Holzbauingenieure Schweiz AG planned the façade replacement and managed this sub-project.

The construction
The spruce wood construction is not simply the basis for the facade. Since wood only chars slowly in the event of a fire and still has a load-bearing and insulating effect with its residual cross-section, it is also the fire protection layer for the steel parts underneath.

The challenge
The challenge in designing the facade was to use the wooden elements to compensate for the unevenness and tolerances of the concrete structure. Steel elements were able to accommodate these tolerances and the punched-through concrete slabs.

Construction Data

- Structural timber FI/TA


Construction costs

- Construction costs 105 million francs

- Construction costs BKP 214 1.28 million francs


Services of Timbatec

- Planning of the facade with:

- Preliminary project

- construction project

- Devising/tendering

- Construction management and controls

Timberconstruction engineer
Timbatec Holzbauingenieure Schweiz AG


Timber constructioncontractor
Beer Holzbau AG
3072 Ostermundigen


Client
Canton Basel-Stadt
4058 Basel


Architecture
Enzmann Fischer Partner AG
8003 Zurich


General contracting
Zwimpfer Partner Architekten AG
8047 Zurich


Facade planning
Fiorio Fassadentechnik
9524 Zuzwil



Datenschutzhinweis

Diese Webseite nutzt externe Komponenten welche dazu genutzt werden können, Daten über Ihr Verhalten zu sammeln.

Notwendige Cookies werden immer geladen